Structural Steel Work Completes on Torrance Memorial Medical Center

TORRANCE, Calif. (March 1, 2012) — Construction is one step closer to completion on the new $450 million Torrance Memorial Medical Center Patient Tower.  Located on the existing medical center site at 3330 Lomita Boulevard in Torrance, Calif., the project reached a major milestone when construction workers placed the final piece of structural steel on the 398,350-square-foot facility. McCarthy Building Companies, Inc., is serving as general contractor for the project which began construction in February 2010. During the steel erection phase, iron workers from Herrick Steel placed 5,820 pieces of structural steel within three months in order to build the frame for the new tower. The project team celebrated the topping out of structural steel on February 23, 2012 during a barbecue luncheon held for…